In-Kinds Needed

In-Kinds Needed

Conversations with the builders are underway regarding a start date for construction.

To reduce construction time, reduce cost and increase the amount of park features we are seeking in-kind donations. If we get enough in-kind donations, we will be able to construct a concrete mini ramp within the park footprint, thus achieving the full park design.

Below is a list of the higher cost items.

If you, or know somebody who has a lead on any of the items below, please contact [email protected]

Lodging

The construction is expected to last 8 to 12 weeks. We are seeking a house/condo in the area that can house the construction team (8 adults) for the duration of the time.

Concrete

Securing a concrete discount or donation will amount to a HUGE savings for us.

  • 140 cubic yards of concrete
  • 40 bags of concrete

Equipment

This equipment will be used for construction time frame of 8 to 12 weeks.

  • Mini-Excavator
  • Bobcat or skid steer

Materials

  • Rebar (#3): 20ft. Sticks | 650 Sticks
  • Rebar (#4): 20’ Sticks | 100 Sticks
  • Rebar Ties: 2 Cases
  • 2’x4’x16’ Spruce 200 Units
  • 3⁄4” Plywood AC 25 Units
  • Masonite 5 Sheets
  • Straight Forms – 1×6 | 500 Linear Feet
  • Round forms – 1×6 Miratek 100 Linear Feet
  • Steel Stakes (24” long) 100

Keep Pushing

Having a baseline understanding of the in-kind donations will help the builders finalize their plans for a start date. We’re almost there. Keep pushing.